Update: This operation has been rescheduled for 9 p.m. tonight to work around forecasted rain and may be rescheduled or delayed pending weather conditions.
Columbia, S.C.
(May 17, 2024) – Starting tonight, SCDOT will shift traffic from the existing bridge on Broad River Road over Interstate 20 onto a newly constructed bridge as a part of the Carolina Crossroads Project.
The traffic shift is scheduled to begin at 9 p.m. on Friday, May 17, and is expected to be completed by 4 a.m. on Saturday, May 18.
The traffic shift will involve transitioning traffic from the existing bridge to the new bridge to allow for demolition and reconstruction of the existing bridge. Drivers should be aware that all lanes of traffic on Broad River Road will be affected.
As a result of the traffic shift, there will be a new traffic pattern for drivers exiting I-20 Westbound and taking the off-ramp onto Broad River Road toward Columbia.
Message boards and construction signs will be placed along Broad River Road and the I-20 Westbound off-ramp throughout the duration of the traffic shift. Law enforcement will also be onsite to direct traffic.
Drivers are advised to use caution and plan accordingly in case of delays. Dates are subject to change pending weather conditions. Visit the project webpage
scdotcarolinacrossroads.com