Project Name | RFQ | Announcement of Short-listed Teams |
RFP Industry Review | Final RFP | Public Announcement | STIP |
---|---|---|---|---|---|---|
Long Point Road Interchange Improvements | Q3 2025 | Q4 2025 | Q4 2025 | Q1 2026 | Q3 2026 | STIP |
Bridge Package 27 | April 4, 2025 | May 12, 2025 | May 12, 2025 | June 3, 2025 | June 27, 2025 | NA |
Bridge Package 21 | June 2025 | August 2025 | August 2025 | September 2025 | January 2026 | NA |
Bridge Package 22 | February 2026 | March 2026 2025 |
March 2026 | April 2026 | August 2026 | NA |
Bridge Package 23 | August 2026 | September 2026 | September | October 2027 | February 2027 | NA |
Bridge Package 24 | Q1 2027 | Q1 2027 | Q1 2027 | Q2 2027 | Q3 2027 | NA |
Mark Clark Expressway Extension | 2027 | 2027 | 2027 | 2027 | 2027 | NA |
Bridge Package 25 | 2027 | 2027 | 2027 | 2027 | 2028 | NA |
Bridge Package 26 | 2027 | 2027 | 2027 | 2028 | 2028 | NA |
Bridge Package 28 | 2028 | 2028 | 2028 | 2028 | 2029 | NA |
Lowcountry Corridor West | 2028 | 2028 | 2028 | 2028 | 2028 | STIP |
Carolina Crossroads Phase 3 – I-20/26 & I-26/126 System Interchanges, St. Andrews Road at I-26 Interchange, and Bush River Road at I-20 Interchange | 09/15/22 | 11/30/22 | 12/01/22 | 02/15/23 | NA | |
Carolina Crossroads Phase 3D – I-26/126 System Interchange Design Build Project | Q3 2025 | Q4 2025 | Q4 2025 | Q1 2026 | Q3 2026 | STIP |
Carolina Crossroads Phase 3E – I-20/26 System Interchange and St. Andrews at I-26 and Bush River Road at I-20 Service Interchanges Design Build Project | 2029 | 2029 | 2029 | 2029 | 2030 | STIP |